martes, 7 de diciembre de 2010

Service Provided to M/V Asian Sun 2010






M/V Asian Sun.

Complete Overhaul Done on Main Engine MAN B&W 7L58/64. M/V Asian Sun
Description

Taken Crankshaft Deflection: a main engine crankshaft deflection was taken while the vessel is afloat prior to dry-docking. A second set of deflections was taken at the end of the repair period with the vessel afloat. Exclude open/reclose of crankcase doors. Cleaning - if needed - not included. Reading afloat with vessel alongside shipyard's berth. All readings were recorded and submitted to the attending Owner’s superintendent.

11.2. Main Engine Charge Air Cooler: Was done by: InServ
Was renewal the air cooler element using owners supplied spare. Pressure test was carried out and refitted back to engine.

11.3. Main Engine Overhaul: Was done by: InServ. Supervised by: Owners Contractors. The Main Engine was overhauled due running hours basis under the supervision of Manufacturers representative. All spare parts were owners supply.
a) Were remove rocker arm covers, rocker arms, cylinder heads and pistons. Cylinder heads were cleaned and overhauled according to manufacturer’s instructions, including all valves being overhauled and seats being lapped in as required. Piston skirts were dismantled and cleaned the piston crown were renewal for remanufactured Crowns. Cylinder liners were honed using ships honing machine. All measurements were record and presented to owner’s representative. On completion all parts were reassembled with new spare parts as required and refitted. All clearances were adjusted as per manufactures recommendations.
b) Were withdrawal, cleaning and refitting with new seal rings each cylinder liners. Included cleaning as required of water spaces.
c) Was removed, inspected and refitted one set of connecting rod bearing shells. Based on condition of bearing shells these weren’t renewed rather than refitted.
d) Were loosen, for inspection and refitting of eight (8) set main bearing shells and one set of Thrust bearing. Before the bearings inspection this activities was aborted. Tighten again all main bearing bolts.
e) Cost to remove one fuel pump. Pump to be dismantled and cleaned and spare parts as required, including if required, the pump element. Upon reassembly, pump to be refitted and timing checked. It Job was done by Ship‘s crew.
g) Main Engine Vibration damper inspection. The Main Engine Vibration damper was renewed due running hours basis under the supervision of Manufacturers representative. This job included, pipe removal, pumps, flooring plates, covers and cutting-Welding supports with Ciramar' Staff help.

11.4. Thermal Oil Installation:
Supervised by: Chief Engineer.
The vessel is fitted with one Aalborg Thermal Oil Heater Type V4-0-TFO-010 with capacity 800 KW and one Aalborg Thermal Oil Economizer type EXV 568-41-57.0-600 with capacity 1,000 KW
Ship’s crew will open up both for presentation to Class surveyor.
Two safety valves were transport ashore to certified Calibration center to calibrate. During the testing inspection the valve started to open at 0.3 Bar, The calibration center didn’t adjust the valves because they need to be repaired. The opening pressure of 10 Bar wasn’t reached, because the valve started to open with less pressure.

Additional Works:
Supply Bolts and Gasket material to assemble charge air cooler.
Done maintenance to charge air cooler housing.
Supplied Gasket Material and built Gasket to assemble all the pipes that were dismantled during M.E. Vibration Damper Renewal.
Prepared Access for Inspect Main Bearings in M.E. Both Side: Cut supports and removed flooring plates and refitted back.
Built charge air cooler base support plate.
Supplied O-rings to assemble all the pipes that were dismantled during M.E. Vibration Damper Renewal.

Service Provided to M/V Windermere 2010





M/V windermere.

Main Engine – Type: Hitachi MAN 7L35MC Mk 6

"F.2.11 MAIN ENGINE CHARGE AIR COOLER:
Charge air cooler was removed from the engine and
chemically cleaned on both the air side and sea water side. On
completion of cleaning to the satisfaction of the Owner's Representative, the
coolers was pressure tested to 5 kg/cm2 with the Owner's
Representative in attendance.
The coolers was refitted to the engine room using gaskets supplied by InServ.
End covers were painted. Air cooler housing was cleaned and painted (adittional Work)."

F.2.12. Main Engine Turbocharger: Type: MHI MET 42SD: Main engine turbocharger was opened up and dismantled for Class survey. Rotor and compressor were removed and transported to turboshop, ( ash blasted and dynamically balanced were done by Seaboard) . Nozzle ring, labyrinth sealing and diffuser were removed, cleaned and checked. Filter and silencer were cleaned. Rotor was transported back to vessel and turbocharger was closed up in good order using Owner's supplied new seals, bearings and oil pumps.

F.2.10. Main Engine Governor: Make: Woodward Type: PG-A Governor to be removed to certified workshop for routine overhaul. Unit will be refitted, tested and adjusted to satisfaction of the attending Superintendent.
Governor was taken to certified workshop for routine overhaul (Done overhaul).
Supplied governor overhaul Kit.
Governor was removed, adusted and refitted back to engine after overhaul.
Governor transported to Governor shop and transported back to ship.

F.3.1. Auxy Engine Charge Air Coolers: Charge air coolers were removed and transported to InServ workshop for Chemical cleaning of sea water and air sides. Cooler to be pressure tested on completion of cleaning to Owner's representative satisfaction. Coolers were returned on board and refitted using InServ supply new gaskets. Sea water pressure 2.5 Kg/cm2. End covers were cleaned and painted with InServ supplied paint.

Mechanical Assistances for A.E. , M.E and Mechanical works, supplied four Technicians.
One (1) Service "A" Mechanic .
Three (3) Sevice "B" Mechanics.
Supplied 20 nuts and 20 washers for A.E.

Service Provided to M/V Zia Belle 2010.





M/V Zia Belle

Description

"E001-03 MAIN ENGINE AIR COOLER:
Charge air cooler was removed from the engine and chemically cleaned ashore on both the air side and sea water side. On completion of cleaning to the satisfaction of the Owner's Representative, the coolers was pressure tested to 5 kg/cm2 with the Owner's Representative in attendance.
The coolers was refitted to the engine room using gaskets supplied by InServ.
End covers were painted."

Was repaired the charge air cooler element stanless steel screen cover.
Main Engine Air Cooler cover (Upper and Lower of water side) to be check, due to excessive air leakage, the covers were repaired.

CRANES AND DERICKS:
CRANE TYPE: MCVC 3426-36-29,2(90-14)(150-9)(6-31,2) MACHINE NO: K4018-5196 KRISTIANSAND - NORWAY. Was Dismantled and checked the condition of bearings and sheave shell after inspected was replaced the bearings, with new Owner's Supplied (was required bearing renewed as per the attending Port Engineer’s recommendations).
Were supplied 24 bolts M19, 24 nuts M19, 24 pressure washers M19 , and 20 nuts M20 for crane assembling.

Cranes And life boat hoses:
Dismounted and mounted 34 hoses from the two provisioning cranes and life boat, were installed new hoses and pressure tested were done before installed.
Were supplied 34 new hoses for two provisioning cranes and a life boat.

Bow Winch:
Was dismounted and dismantled, cleaned, mounted and assembled the Bow winch.
The bow wincher was transported to machining shop for shaft repair and roller bearings bushings replacement and transported back to ship.
Supplied six bearing bushings. Dismounted old and intalled new ones.
Repaired winch shaft.

M.D. vent pipes: Diameter 12". (13) pcs. Total. Renewed flange bolts and gaskets.
"E001-04 Exhaust & Auxiliary Boiler. Maker: GEKA WARMER TECHNIC-ENERGY SYSTEM
Type: TH Z10S. Capacity: 1300 kW. Pulled out and transported to safety valve workshop, then carried out overhauling, calibration and certificate was issue by relieve valve certified company."

M.E. and Ship Automation inspection service: an automation Engineer and electrical assistant were used for the inspections and solve ship automation failures.

Life Boat Inspection: Supplied a service Engineer and a service mechanic to assist to the life boat specialist during life boat and cranes inspection.
Mechanic Service Engineer.
Service Mechanic.

Supplied 4 oil seals for the ship cranes, 4 belts to a compressor and a pulley for compressor.
Supplied 20 stainless steel spacers of Φ 40mmX 2.5 for the life raft davit..
Supplied 2 stainless steel spacers of outside Φ 164 mmXinside Φ 130 mmX thickness 2.5 mm for the life raft davit.
Supplied 4 griserine manometers, 2 range of 0-20 Bar and 2 range of 0-400 Bar.
Mechanic inspection of engine boat Yanmar and transportation to ashore workshop. Engine was damaged, was not possible repaired. Not got spare parts in our country.

Service Provided to M/V Alexandra 2010.







M/V Alexandra.

Engine running hrs:. 100,933
Engine No: Main engine
Model: MAN B&W 8L48/60
Use: Main propulsion engine.
Speed: 514 RPM.
Power: 6,980 Kw.
Fuel: heavy fuel oil.

2-Persons involved:
InServ staff.
3-Client’s initial request:
A- Disassembly main engine units # 1 And # 5. Do Turbocharger inspection, Dismantle Charge air coolers for cleaning, pressure test and reassembly.

B- Do complete overhaul to Auxiliary engine # 2, Do Turbocharger inspection, Disassembly air cooler for cleaning, pressure test and reassembly.

4-Work Description:
This service was started on July.15.2010 as per client request. The Service is in details as follow:


1) Main Engine Taken Crankshaft Deflection (1&2): Taken Crankshaft Deflection: Upon the vessel's arrival, prior to any changes in ballast condition and while the vessel is still afloat, crankshaft deflections were taken and recorded. Upon completion of all repairs, and with the vessel once again afloat and ballasted as original, two further set of deflections was taken and recorded (After docking and after engine running-in). All readings taken were submitted to the Owner's Representative and the vessel's Chief Engineer.

2) M.E. Overhaul of cylinder heads (# 1, # 5 and one in Spare):
Disconnected of conducts and other elements to removed cylinder head, cleaned and inspected same and afterwards reassembled with new joints.
Cylinder head were removed and refitted on position on completion and tight.
Cylinder heads were transported to/from ship workshop and complete dismantled.
Mechanical and chemical cleaning of cylinder heads and checking of all elements.
Dismounted, refitted and inspected of safety valves, rotocap. Dismounted of inlet and exhaust valves and mounted. Cleaned and grinded of valves and seats.

3) M.E. Pistons & Connecting rod No. 1 and 5.
Pistons with connecting rods were removed and transported to/from ship workshop. Piston and connective rod were dismantled; all elements were cleaned, inspected and calibrated. Included piston chemical cleaning and renewal of piston rings - Owner's supply - and measurement of piston groves.
Renewed of connecting rods bearings lower/upper bearing shells.
Submitted record of clearances.

4) M.E. Piston crowns No. 1 and 5.
Piston crown cooling galleries were cleaned.
Taken measurements.

5) M.E. Cylinder liners No. 1 and 5.
Done Liner mechanical cleaning of liner outer side and cylinder block inner side and carbon removed from cylinder inner side. Liner inspected and measured.

6) M.E. Done Mechanical honing after inspected liner No. 1 and 5. (The honing was done two times in the same cylinders due to water arrived inside the cylinder after 1st honing). A cooling water valve wasn’t close properly.

7) M.E. Fuel Injection Pumps No. 2,3,5 and one in spare.
Injection pumps were removed and transported to/from ship workshop, refitted back on completion.
Injection pumps were dismantled, all parts were cleaned and checked, and damaged parts were renewed with owner's supplied spare parts.
Injection pumps were assembled in pump test stand and regulated.

8) M.E. Charge Air cooler:
Was dismantled and cleaned thoroughly by chemical water and air sides and carry out pressure test . After that was reassembled to Main Engine in good order.

9) Turbo chargers M. E. MAN-B&W, NA 48 TM: Open up bearings covers and inspected bearings and pumps. Removed air inlet casing and checked the rotor. Clean dismantled parts, checked clearances and reclosed with same bearings. Removed gas inlet casing, clean nozzle ring and reinstalled.

10) Auxiliary Engine No. 2, MAN/B&W L20/27 720 KW, Complete overhaul: A1. Allowed to dismantle all Cylinder heads. A2.Cylinder heads were overhauled with replacement worn details. A3. Crank bearings were disassembled and renewed. A4. Pistons were withdrawn and disassembled with new piston rings. A5. Cylinder liners were measured and honed. A6. All parts were cleaned and measured. A7. All worn parts were replaced. A8. Engine was assembled. A9. Running test was performed. Spare parts were supplied by Owner. Submitted calibration report.

11) Auxiliary Engine # 2 taken three Crankshaft Deflections: crankshaft deflections were taken and recorded before maintenance. Upon completion of all repairs two further set of deflections were taken and recorded. All readings taken were submitted to the Owner's Representative.

12) A.E. Turbo chargers MAN-B&W NR 15/R: D/G N°2.
Open up bearings covers and inspected bearings and pumps. Removed air inlet casing and checked rotor. Cleaned dismantled parts, checked clearances and reclosed with same bearings. Submitted calibration report.

13) DG Nº 2 Air cooler.
Was dismantled and transport to/from ashore work shop, cleaned thoroughly by chemical water and air sides and carried out pressure test . After that was reassembled to Main Engine in good order.

14) Fuel Injection valves No. 1,2,3,4,5,6,7 and 8.
Fuel Injection valves were removed and transported to/from ship workshop, refitted back to engine on completion.
Fuel Valves were dismantled, all parts were cleaned and checked and damaged parts were renewed with owner's supply.

15) Fuel Injection valves in Spare No. 1, 2 and 3.
Fuel Valves were dismantled, all parts were cleaned and checked and damaged parts were renewed with owner's supply.

16) Cleaned Main Engine Crankcase: the crankcase was cleaned completely two times.

17) Repaired two centrifugal Separator distributors: were renewed the guide discs and was mechanized the F.O Distributor.

18) Removed old auxiliary engines ventilators, supplied and installed new ones (Dayton Brand).

19) Auxiliary Generator # 1 Governor. Done complete Overhaul Was inspected, adjusted and calibrated and assembled using overhaul kit.

20) Repair auxiliary engines Governor in Spare. Done complete Overhaul, Was inspected, adjusted and calibrated and assembled using overhaul kit.

21) A.E. # 2 Replaced flexible turbocharger air discharge hose.

22) Inspected Auxiliary engines automation and controllers system.

Service Provided to M/V Monarch Empress 2010






M/V Monarch Empress.

Model: Deutz BV M540/Wascor 12V
Use: Main propulsion engine/Auxiliary Engine.
Speed: RPM.
Power: Kw.
Fuel: heavy fuel oil/Diesel.

2-Persons involved:
InServ staff.
3-Client’s initial request:
A- Take Crankshaft Deflection: Upon the vessel's arrival, prior to any changes in ballast condition and while the vessel is still afloat, crankshaft deflections are to be taken and recorded. Upon completion of all repairs, and with the vessel once again afloat and ballasted as original, a further set of deflections are to be taken and recorded. All readings taken are to be submitted to the Owner's Representative and the vessel's Chief Engineer.

B- Remove the 12 cylinder heads and transport to workshop for maintenance and refit back to engine. Spare parts owner Supply.

C- Auxiliary engine turbochargers: Dismantling and transport to workshop for complete overhaul. Spare Part cost will be charge to the Invoice.

Service Provided to M/V Baffin Strait 2010




M/V Baffin Strait.

I Mechanical Ship Repair Assistance: 3 Technicians full cooperation in Ship mechanical work by more than 5 months.

Service Provided to M/V AmericanBorg 2010





M/V AmericanBorg.
Engine running hrs: 15,131.
Engine No: M.E.
Model: Wartsila Diesel Engine 8L.46
Use: Main propulsion engine.
Speed: 514
Kw:
Fuel: heavy fuel oil.

2-Persons involved:
InServ Staff.

3-Client’s initial request:
1) To transport ashore workshop the main engine air cooler (in Spare) for repair cooling water leaking.
2) To transport ashore workshop the M.E. lube oil pump for programmed maintenance and inspection.
3) To Asisst in main engine complete overhaul.

4-Work Description:

This service was started on May.126.2010 as per client request to transport to workshop for repair main engine charge air cooler and do M.E. lube oil pump maintenance.

A) Main Engine Charge Air Cooler (In Spare):
The Charge air cooler was transported and brought to workshop for repair leaking cooling water (were found four bursted tube they were plugged), chemical cleaning was done, gaskets renewed and painted.
After repairing and cleaning the charge air cooler was pressure tested to 5 Bar.
The charge air cooler was brought back to ship.

B) Main Engine Lube Oil Pump:

Main Engine Lube oil pump was transported to workshop was inspected and done programmed maintenance according Wartsila diesel manual.
The main Engine lube oil pump was taken back to ship.

Service Provided to M/V Kempton 2010





M/V Kempton.-
Engine No:
Model: MAN B&W 6S35MC/Yanmar 6NY16L.
Use: Main propulsion engine/Auxiliaries Engine.
Speed:
Kw:
Fuel: heavy fuel oil.

2-Persons involved:
InServ Employees.

3-Client’s initial request:
A- Disassembly main engine charge air cooler, cleaning, pressure test, transporting and reassembly.

B- Disassembly air coolers at auxiliary generator set # 1 and 2, cleaning, pressure test, transportation and reassembly.

4-Work Description:
This service was started on March.06.2010 as per client request to dismantling main and auxiliaries engines charge air coolers to do chemical cleaning, inspection and pressure test.

Main Engine Charge Air Cooler.
This air cooler was dismantled, inspected, painted and cleaned externally and internally.

A lot of pipes were blocked with sediment in sea water side and all of them were unblocked.

Pressure test was done to this charge air cooler at 5 bar pressure at water side and any leakage was present, later was installed.

Auxiliary Engine air cooler.

These air coolers at auxiliary engines # 1 and 2 were dismantling and it were washed with the appropriated chemical, also we made hydrostatic test and after that they were installed on the auxiliaries engines.

Pressure test was done to this charge air cooler at 4 bar pressure at water side and any leakage was present.

During the transportation the air cooler # 2, was drooped and appeared a crack of aprox. 6 inches in an air cover side, the cover was repaired and tested satisfactorily

Service Provided To M/V Grasmere 2010





Engine No: 3682
Model: Hitachi MAN Type 6L35MC Mk6.
Use: Main propulsion engine.
Speed: 170
Power: 4252 BHP
Fuel: heavy fuel oil.
2-Persons involved:
InServ staff.
3-Client’s initial request:
Disassembly main engine charge air cooler, cleaning, pressure test, and reassembly.

4-Work Description:
This service was started on april.05.2010 as per client request to dismantling main engine charge air cooler to do chemical cleaning, inspection and pressure test.
A- Main Engine Charge Air Cooler.
This air cooler was dismantled, inspected, painted and cleaned externally and internally.
Air cooler element was removed for chemical cleaning of sea water and air sides. Size 1.23m x 0.6m x 0.83m approx dry weight .75Tonne. Cooler was pressure tested on presence Owner's representative Shief Engineer, was returned and refitted using new gaskets. Had 4 tubes plugged with wood plugs,Were replaced 8 wood plugs and installed Nylon Plugs. Were reconditioned the back cover division line hole threads (Two).
Dismounted and mounted sea water pipes end covers were cleaned and painted with Apexior paint. Zinc anodes were cleaned.

B- Charge air cooler housing: Done maintenance it was removed a lot of scrap metal (rust metalic), more than 10 Kg were removed and internal housing was painted.

Service Provided to M/V Forest Panama 2010







Service I.- M/V Forest Panama

Engine No: 3237
Model: Wartsila Vasa 16V32
Use: Main propulsion engine.
Speed: 750 RPM.
Power: 5,520 Kw.
Fuel: heavy fuel oil.


2-Persons involved:
InServ staff.
3-Client’s initial request:
A- Disassembly main engine units A3, A6, B1, B5, B6. Charge air coolers A side, B side, Spare #1, Spare # 2 for cleaning, pressure test, transporting and reassembly.

B- Disassembly air coolers at auxiliary generator set # 1, 2 and 3, for cleaning, pressure test, transportation and reassembly.

C- Replace shaft engine sealing rings and gaskets; Clean Crankcase; Inspect HFO Separator failure; disassembly, Clean with chemical, pressure test ; reassembly Steam Heaters #1 & #2, and Dumping cooler And Repair ME expansion Joint gas leak.

4-Work Description:
This service was started on March.24.2010 as per client request. The Service is in details as follow:

I Main Engine:

1) Taken Crankshaft Deflection (1&2): Upon the vessel's arrival, prior to any changes in ballast condition and while the vessel is still afloat, crankshaft deflection was taken and recorded. Upon completion of all repairs, and with the vessel once again afloat and ballasted as original, a further set of deflection was taken and recorded. All readings taken were submitted to the Owner's Representative and the vessel's Chief Engineer.

2) Overhaul of cylinder heads (A3, A6, B1, B5, B6): Dismantled and assembled, cleaned the underside, inlet and exhaust valves and ports. Inspect cooling spaces and clean. Inspect the valve rotators. Checked rocker arms.
Were installed new exhaust valves to Cylinder head A6; Cylinder head B1 was found without rotocaps in the inlet valves, these were installed, was changed an exhaust valve and short springs by long. Cylinder head B6 were changed two exhaust valve and were installed two used valve and were changed short springs by long, also was changed a inlet valve by used one. Were left two cylinder heads ready to use for spares. Were mounted fuel injection valves prepared by ship Crew in the respective cylinder heads.

3) Were inspected and completed the two (2) cylinder heads that ship had in spares and they were installed on cylinders A3 and B5.

4) Inspect the cylinder liners (A3, A6, B1, B5, B6, Spare # 1, Spare # 2): Dismantled and assembled. Measured the bore using form No. 3210V014. Honed the liners. Renewed the anti-polishing ring. The cylinder A6 was replaced by new short cylinder liner , All cylinder liners measured were taken any of they were over wear… but the old cylinder liner A6 was left for spare and it can be used only in extreme emergency due a lot of corrosion in the cylinder liner collar. See bottom the measurement report.

5) Disconnected cylinder liner and cylinder head A6: these pulled out together, due to the cylinder had high water leakage and hard corrosion in the cylinder liner collar. Our team avoid to transfer this unit to our workshop and done it disconnection on site.

6) Was Rented an external Cylinder liner honing machine: to hone the Cylinder Liners (A3, A6, B1, B5, B6, Spare #1, Spare #2). Cylinder liners honing were done.

7) Inspected the pistons (A3, A6, B1, B5, B6, one in spare): Composite pistons were dismantled for inspection of mating surfaces between piston skirt and piston crown. Inspected and cleaned oil spaces. Pulled, inspected and cleaned. Checked the height of the ring grooves, use form No. 3211V016. Checked the retainer rings of the gudgeon pins. Replaced complete set of piston rings. The piston B6 has over wear in the first piston crown groove it was replaced by reconditioned one that ship had in spare. See bottom the Measurement report. When the piston A3 was taken out appeared the first piston ring broken.

8) Connecting rods (A3, A6, B1, B5, B6): Replaced big end bearings. Inspected mating surface serrations. Measured the big end bore, used form No. 3211V015. Inspected the small end bearings. Were replaced the screws of connecting rod A6. See measurement report below. The connecting rod big end bearings B6 was found with deep peel.

9) Main Engine Crankcase: was cleaned and closed after finish engine works.

10) AIR COOLERS (A Side, B Side, Spare #1, Spare #2): Makers: GEA.
Type: 68/26/22/2-ESV-S99-20K 192; Size : 830 x 640 x 470 mm.
ME Air Coolers cleaned by chemical, painted and pressure tested.
DETAILS:
A1. Dismounted the cooling water inlet and outlet pipes, side covers, reversing chamber.
A2. Removed cooler elements. Putted elements to workshop and returned
A3. Installed the cooler elements. Assembled covers and pipes with new gaskets.
A4. Carried out pressure test.

11) Cylinder heads valves clearance: All cylinder head valves were adjusted and calibrated.

12) GOVERNOR: SIZE/TYPE:
Governor : Maker - Woodward ; Type: PGE 58. JOB AIDS: Transported from/to vessel.
DETAILS:
1. Governor removed from engines and transported to authorized workshop.
2. Governor was examined. Worn parts not found.
3. Governor was reinstalled back to engines. Engine running tested to ensure proper working operation pending.

13) Main Engine shaft bearing: replaced sealing rings and gaskets. The old sealing rings had a big open clearance in terminals, we suspected that is was the first reason for oil leakage and also didn’t have the appropriated gaskets.

II Auxiliary Engines:

1) AIR COOLERS, Aux engines size 240x200x120 mm. Air Coolers cleaned by chemical and tested.
Pressure test from water side. carried out.
A1. Dismounted the cooling water inlet and outlet pipes, side covers, reversing chamber. A2. Removed cooler elements. Putted elements to workshop and returned. A3. Installed the cooler elements. Assembled covers and pipes with new gaskets. A4. Carried out pressure test.

III Auxiliary Equipments:

1) HFO Separator WHPX-405: “Program failure Not discharge alarm “ was inspected and repaired. Were reviewed all operation and program parameters, checked all electrical actuators MV 1, MV10, MV15, MV16. Was found feed water obtrusions in the valve MV 10 and MV 15. The separator was tested and putted in operation; it was left ready for operation. Our recommendation is that ship has to order the respective water flow disc to the solenoid valves block and change the old one prepared and installed by the ship crew.

2) Heat Exchangers and Heaters: Two (2) HFO Steam Heaters and one (1) dumping cooler: were dismantled Chemical cleaned, painted, tested, inspected and mounted back.

3) Main Engine Expansion Joint (Exhaust Gas Bellow): Repaired gas leak.


5) Measurement Reports.
A) Piston Crown Rings Grooves.
B) Connecting Rods Big End Bearings Bore.
C) Cylinder liners bore.
D) Crankshaft deflection.