lunes, 28 de febrero de 2011

Service Provided to MV Ingrid Gorthon 2011




Main Engine , Hitachi Sulzer 6RND68, 7280 KW 2-STROKE and boilers.
M/V Ingrid Gorthon

Description
16.01 (1) Upon completion of all repairs and with the vessel once again afloat and ballasted as original, a set of deflections was taken and recorded (After docking). All readings taken were submitted to the Owner's Representative and the vessel's Chief Engineer.
16.06 MAIN ENGINE GOVERNOR:
Governor was overhauled, adjusted and refitted back to engine.
SIZE/TYPE:
Governor : Woodward ; Quantity : 1 set ;Maker: Woodward Governor Comp. Tokyo, Japan
Type : PGA 58 with Actuator HF-301-HY 1P
Designation A 8555 845 ; SN 1497842
Governor drive shaft speed 250-1375 RPM ;Control air: 10-64 PSI
SURVEY/ TEST:
Visual inspection by Superintendent or Chief Engineer.
Running test.
Inspected governor in place. Dismounted, transported to governor shop for bank tests and refitted back to engine.
Governor basic overhauled, dismantling and supplied of overhauling kit.
Extraordinary repair was done in Governor: were replaced the Oil gear pump and valve casing, pilot valves, oil gear pump, the speeder spring, governor shutdown valve and oil pump driving shaft. All these because the governor didn’t reach the normal oil pressure and respective speed range.
17.01 Auxiliary Boiler: The following valves were removed from the boiler and transported to workshop for Overhaul: Valves were disassembled, cleaned and re-seated and presented to the Classification Surveyor and Owners Representative for inspection.
Valves were reassembled in good order with new packing and joints supplied by InServ. All bolts were lubricated with ‘COPASLIP’ or similar high temperature anti-seizing compound.
The safety valves were done complete overhaul and calibration. Dismounted and refitted back to boiler.
1. Safety Valve. Done complete overhaul at certified workshop, the valves were Dismounted and Refited back to boiler DN40/PN40; 2 PCs
2. Main Steam Valve DN80/ PN40 1 PCs
3. Feed Water 32/PN40 2 PCs
4. Feed Water (SDNR) 40/PN16 2 PCs
5. Scum Valve (SDNR) 25/PN40 1 PCs
6. Blow Down (SDNR) DN25/PN40 1 PC Plug cock 1 ½ - 2PCs
7. Air Escape Valve DN15/PN40 1 PC
8. Gauge Board v/v BSP 1/2” 2 PCs
9. By-Pass DN50/PN50( Automatic)1 PC PN16- 1PC, PN40-1PC
10. Circulation water to Exh. Boiler DN40/PN40 1 PC
11. Steam water fm Exh. Boiler DN65 PN40 1 PC